| Objective |
Disaster Prevention Environmental Conservation Infrastructure Improvement |
|---|---|
| Techniques | Slope Protection/Environmental Conservation |
| Period | 03/2010~11/2013 |
| Comment |
Isawa Dam, a largest rock fill dam in Japan has completed. We conducted grouting for the foundation of the dam, as well as slope work for the surrounding ground and roads of the dam. (3/2005~11/2013) |